SafeTrack is an extensive maintenance program currently taking place on WMATA's Metro system. The program is intended to make major repairs to rehabilitate the system, accomplishing about three years of work in a single year. The program is in reaction to various safety issues and recommendations which have plagued the system in recent years.
SafeTrack will have a significant impact on commuting in the Washington DC area. As part of the program, the Metro system will close at midnight every day, and will include 15 "Safety Surges", listed below, which will show down portions of each line. While WMATA and local municipalities intend to provide special bus service, each of these surges is likely to be quite disruptive as commuters seek alternatives.
It is important to be aware of these surges and understand how they will affect you.
For extensive details on each surge, please visit WMATA's page on SafeTrack.
Surge Schedule
Date | Duration | Lines | Impact | Area Affected |
June 4-16 | 13 days | Orange Line, Silver Line | Single Tracking | Ballston Station - East Falls Church Station |
June 18-July 3 | 16 days | Orange Line, Blue Line, Silver Line | Segment Shutdown | Eastern Market Station - Benning Road Station |
July 5-11 (starts 8pm July 5) | 6 days | Yellow Line, Blue Line | Segment Shutdown | Reagan Station - Braddock Road Station |
July 12-18 | 7 days | Yellow Line, Blue Line | Segment Shutdown | Pentagon City Station - Reagan Station |
July 20-31 | 12 days | Orange Line, Silver Line | Single Tracking | Ballston Station - East Falls Church Station |
August 1-7 | 7 days | Red Line | Single Tracking | Takoma Station - Silver Spring Station |
August 9-18 | 10 days | Red Line | Single Tracking | Twinbrook Station - Shady Grove Station |
August 20 - September 5 | 17 days | Yellow Line, Blue Line | Single Tracking | Franconia-Springfield Station - Van Dorn Street Station |
September 9 - October 20 | 42 days | Orange Line | Single Tracking | Vienna Station - West Falls Church Station |
October 10 - November 1 | 23 days | Red Line | Segment Shutdown | Fort Totten Station - NoMa-Gallaudet (New York Ave.) Station |
November 3-11 (Starts 10pm Nov 2) | 9 days | Orange Line, Silver Line | Single Tracking | West Falls Church Station - East Falls Church Station |
November 12 - December 6 | 25 days | Yellow Line, Green Line | Single Tracking | Greenbelt Station - College Park Station |
December 7 - 24 (Except am Dec 17) | 18 days | Blue Line | Segment Shutdown | Rosslyn Station - Pentagon Station |
January 2-13 and 23-Feb 3 (Starts 10pm Jan. 22) | 24 days | Yellow Line, Blue Line | Single Tracking | Braddock Road Station - Van Dorn Street Station |
March 6-19 | 14 days | Orange Line, Silver Line | Single Tracking | East Falls Church Station - West Falls Church Station |